A retail precinct worth more than $100 million has been proposed for the Gladstone Golf Club site in Central Queensland, with developer Tipalea Partners and landowner Yaralla Sports Club planning to lodge an application with Gladstone Regional Council in December 2026 for a centre carrying about 25,000sqm of large-format retail and more than 700 on-grade car spaces.
The plans for the Kin Kora Homemaker Centre were reported by Inside Construction, which says the scheme has been designed by i2C Architects and is expected to generate about 1,200 jobs during construction, plus 400 ongoing positions once the doors open. Subject to planning and other approvals, that’s pencilled in for 2030.
Preliminary leasing talks are underway with national brands and local operators, according to the report.
”Gladstone is growing, but the community still has limited choice”
Tipalea Partners CEO Scott Spanton said the investment would help meet demand for more retail choice across Gladstone and the wider Central Queensland region.
“Gladstone is growing, but the community still has limited choice across a number of major retail categories,” he said.
Spanton said the developer wanted locals in the tent early rather than after the plans were set.
“For us, this is about creating a centre that genuinely works for Gladstone. That’s why we want the community involved early and why we’ll be asking locals what they want to see as the plans continue to develop.”
Tipalea plans to run community Q&A sessions and let residents help name the centre, pick its logo and give feedback on the retail mix. No objectors or submissions have been reported at this stage, which isn’t surprising given nothing has been lodged yet. Everything beyond the announcement, including the detailed design and any construction procurement, remains unreleased.

What a 25,000sqm big-box build actually looks like on the tools
The headline number worth carrying around: about 25,000sqm of large-format retail floor space and more than 700 on-grade parking spaces, generating an estimated 1,200 construction jobs, as announced by Tipalea Partners in November 2026.
On-grade is the word to notice. The parking sits at ground level rather than in a basement, which means the earthworks story here is bulk cut and fill, pavement, drainage and car park lighting instead of a deep excavation, shoring and a structural basement slab. Different gear on site, different sequence, and a civil package that starts earlier and finishes later than it would on a stacked urban centre.
Large-format retail also behaves differently to a tower once the base build is up. Tenancies get handed over as shells and fitted out to each brand’s own spec, so the back half of a job like this is a rolling run of separate fitout packages rather than one continuous program. For sparkies, that typically means base-build distribution and car park lighting first, then tenancy-by-tenancy work on each lease deal as it lands. The exact packaging won’t be known until a builder is appointed, and none has been named.
The timing question for anyone planning a crew
If the application goes in during December 2026 and the centre opens in 2030, that’s a runway of roughly three years from lodgement to trading. Assessment, conditions, any appeals, documentation and procurement all sit in front of the first truck.

Nobody should be hiring off this announcement. What’s worth doing is watching the lodgement on the Gladstone Regional Council development register once it appears, because that’s the document that tells you the real staging, the construction program and the conditions a builder will have to work to. That’s also the point where subcontractors get a read on whether the job is one hit or broken into stages.
For a region where a lot of the commercial work rides on industrial and resources cycles, a $100 million-plus retail job with a 2030 horizon is a different kind of order book entry. It isn’t work for next winter. It’s the sort of project you keep a tab on while you decide whether to put an apprentice on in 2028.
What to watch
The next real milestone is the December lodgement with Gladstone Regional Council, followed by whatever information requests the council issues. After that, the two things that matter for trades are the staging plan and the head contractor appointment, neither of which has been announced.
This story rests on a single published report and the developer’s own statements. Until the application is on the council’s register, treat the floor area, parking count and job figures as the proponent’s numbers, not approved ones.
Frequently asked questions
When will the Kin Kora Homemaker Centre open?
The centre is pencilled in to open in 2030, subject to planning and other approvals, after a planned December 2026 lodgement with Gladstone Regional Council.
How many jobs will the Gladstone retail centre create?
Tipalea Partners expects about 1,200 jobs during construction and around 400 ongoing positions once the centre is trading.
Has the Gladstone golf club retail centre been approved?
No. As of this report, no application had been lodged with Gladstone Regional Council and no builder had been appointed, so the floor area, parking and job figures are the developer’s own numbers, not approved ones.
Sourced from Inside Construction. Original article.