From Monday 14 December 2026, weather permitting, southbound M1 Princes Motorway traffic at Mount Ousley will shift onto two temporary lanes that will eventually form part of the new heavy vehicle bypass. It’s the next staging change on the $402 million Mount Ousley Interchange project at the northern gateway to Wollongong.
The switch was confirmed in a report by Roads & Infrastructure, which said the arrangement is expected to stay in place until the next major traffic change in early 2027. The project is replacing the existing intersection of the Princes Motorway and Mount Ousley Road, a junction used by 50,000 motorists a day, according to NSW Government figures reported by Roads & Infrastructure in November 2026.
That’s the number worth keeping in your head: a good share of those vehicles are trucks dragging freight up and down the escarpment.
What actually changes on the road
The headline change is that the right turn across southbound motorway traffic disappears. Roads & Infrastructure reported the new arrangement “removes the need to turn right across southbound motorway traffic”, which is the movement that has made this intersection a known pinch point.
Four things change at once for drivers:
- Heading to Wollongong, you’ll take the new Mount Ousley Road off ramp and use a dedicated left-turn lane onto Mount Ousley Road.
- Continuing to Keiraville or Gwynneville, you exit at the same off ramp, then use the new southbound access road to University Avenue and the southbound on ramp to rejoin the motorway. Vehicles over 4.6 metres high must also exit there.
- Westbound, you travel along Mount Ousley Road, through the new intersection and over the new bridge, merging with northbound motorway traffic.
- Westbound and heading south from Mount Ousley Road, you use that same southbound access road to University Avenue or to join the M1.
The funding split sits at $321.6 million from the Federal Government and $80.4 million from NSW.
The 4.6 metre line is the one to watch
If you’re running a tilt tray with an excavator chained down, a tipper with a raised body risk, a float carrying a bobcat, or a truck-mounted borer, the over-4.6 metre rule is the part of this change that will cost you time rather than just annoy you.

It means no straight run through on the motorway for high loads at that point. You exit, you take the access road to University Avenue, you come back on. On a single run that’s a few minutes. On a crew doing two or three Illawarra deliveries a day out of Sydney’s south, through December and into early 2027, it adds up into the kind of time that either comes out of the job or out of the bloke driving.
So check your load height before the 14th rather than at the ramp. Anyone quoting Illawarra work that starts in the new year should be pricing the detour into travel time now, not discovering it on the first delivery.
Temporary lanes that aren’t really temporary
There’s a detail in this one that civil crews will recognise straight away. The two lanes southbound traffic moves onto in December are not throwaway pavement. Roads & Infrastructure reported they “will ultimately form part of the new heavy vehicle bypass”, meaning the permanent asset gets built, opened under traffic, and then absorbed into the finished layout later.
That staging is why these projects feel like they drag. Live traffic has to be walked across the site in steps while the permanent alignment goes in behind the barriers, and each step needs its own traffic control plan, its own barrier run, its own line marking and signage changeover. Work that can only happen in night shifts and short possessions takes longer than the same work on a greenfield site.

For anyone on the tools nearby, it also explains the rhythm of the job: a burst of barrier, signage and line marking activity around each switch, then a quieter stretch of construction behind the new traffic layout until the next one.
What to watch
The next major traffic change is flagged for early 2027, so the December layout is the one you’ll be driving for the summer and the first stretch of the new year. No date has been published for that next switch.
Check live conditions before you leave the yard rather than relying on what the route did last week. Transport for NSW publishes traffic updates and project information, and these changes are subject to weather. If it buckets down on the Illawarra escarpment the week before, the switch moves.
Frequently asked questions
When does the Mount Ousley traffic switch happen?
From Monday 14 December 2026, weather permitting, southbound M1 Princes Motorway traffic at Mount Ousley moves onto two new temporary lanes.
How long will the temporary lane layout last?
It stays in place until the next major traffic change, which is flagged for early 2027. No exact date for that change has been published.
What happens to vehicles over 4.6 metres high?
They must exit at the new Mount Ousley Road off ramp and use the new southbound access road to University Avenue before rejoining the M1, rather than running straight through.
Who is funding the Mount Ousley Interchange project?
The $402 million project is funded by $321.6 million from the Federal Government and $80.4 million from the NSW Government.
Sourced from Roads & Infrastructure. Original article.