The cost of building Hobart’s Macquarie Point stadium has risen by $100 million to $1.23 billion, and once the precinct works and delivery costs needed to make it operate are counted, the Tasmanian government’s total lands at $1.54 billion. A construction contract with BESIX Watpac is due to be signed in the coming weeks, with the new budget going to cabinet by 30 November.
Those figures come from an ABC News breakdown of the update Premier Jeremy Rockliff posted to his Facebook page, which lifted the headline stadium number from $1.13 billion to $1.23 billion. The ABC reported the rise was met with “a mix of relief and surprise from those who expected a much higher spike”.
Rockliff’s line on the increase, as reported by the ABC, was that the “cost has changed, but the opportunity for Tasmania has not”. He also said “every generation has a couple of rare opportunities to change their future … for us, this is a golden one”.
“Every generation has a couple of rare opportunities to change their future … for us, this is a golden one.”
What the $1.23 billion actually buys
The core number covers the stadium building itself: seats, roof, grass and fit-out. Everything that makes a stadium a stadium.
It also picks up work already in the ground. The cricket test rig built earlier this year, dilapidation surveys on surrounding buildings, environmental monitoring equipment, and the bulk excavation currently running at the Macquarie Point site ahead of the main build.
That roof isn’t a design flourish, either. The ABC reports it was a condition of the contract with the AFL, and a smaller-scale version was put up to test whether its shadows would cause problems for cricket.
Then come the bits that make the lights turn on
A stadium with no power and no water is a very expensive grandstand. The government has allocated an extra $132 million for stormwater and water upgrades, power upgrades and landscaping across the precinct, which takes the running total to $1.36 billion.
That infrastructure does more than serve the stadium. TasPorts and future development on the site, hotels, restaurants, shops and housing, will all draw on the same energy and water upgrades.
A car park is in that $132 million too, though MPDC chief executive Anne Beach said it “absolutely wasn’t required” for the stadium and would instead act as an “enabler” for the precinct.
On top of that sits $183 million in project delivery costs: consultants, Macquarie Point Development Corporation staff, headworks, building insurance, software, training, and incidentals down to personal protective equipment. Add it up and you’re at $1.54 billion.

The number nobody is publishing
The contingency is missing. The government and the MPDC have decided to keep that figure confidential until the building contract with BESIX Watpac is signed.
Previous estimates did carry it. The last $1.13 billion costing included $174 million of contingency, which the ABC calculates at 14 per cent of the budget. Apply the same 14 per cent to the new total and you add roughly $215 million, for about $1.76 billion all up.
How much the MPDC holds back depends on what the contract says about who wears the risk. Department secretary Kathrine Morgan-Wicks told a recent public accounts committee hearing that assurances before the “final investment decision” went to exactly that point.
“This includes understanding the proposed relationship between MPDC and the lead contractor,” she said.
“For example, the contract cost will be higher as risks are transferred to the contractor, or lower if the state accepts risks.”
That sentence is the whole ball game for anyone who ends up working on this job. Risk that a head contractor prices into its number is risk it has to manage, and the way it gets managed is through the subcontract conditions, the program and the variation process. A state that keeps more risk writes a smaller cheque up front and a bigger one later if something goes wrong in the ground.
Why the price moved, and who else wants your crew
The MPDC cited the war in Iran as a major factor behind the increase, along with Australia’s competitive infrastructure pipeline, which includes the lead-up to the Brisbane Olympics.

That second one is the part Tasmanian subbies should read twice. A nationally tight pipeline means formwork crews, steel fixers, crane operators and services trades can price mainland work instead, and a Hobart job has to beat that number to get them on a plane or a boat. It’s also the argument for local firms getting their capability statements and prequalification in front of BESIX Watpac now rather than after the contract is inked.
The MPDC says it has pushed the other way, confirming it “value managed” the project by $100 million, mainly through the design process and the way the stadium is delivered. Value management is the polite term for taking things out, so the fit-out and finishes scopes are the ones worth watching for changes.
Not everything necessary is inside the budget. The Northern Access Road, priced at $78.9 million, sits outside it because it is a long-standing project funded and run by Building Tasmania. Interest on the extra borrowings isn’t counted either, and those borrowings will flow through a new funding facility for the MPDC. On current numbers, $1.29 billion of the project cost falls to the Tasmanian taxpayer through capital and borrowings, which the ABC reports effectively scraps the $875 million state funding cap Rockliff agreed to in exchange for the upper house vote of Bec Thomas.
What to watch
Cabinet gets the budget by 30 November and approval is expected, with the contract to follow. Rockliff has confirmed ABC reporting that talks have started with the federal government, the AFL, cricket and the private sector about further contributions.
Beach says the numbers stack up. “We’ve had our commercial and legal team, as well as our technical team, look at the detail submitted by [BESIX] Watpac,” she said. “We’ve undertaken an analysis, and we’re confident that we can deliver within that budget,” she said.
For anyone chasing packages, the signature on that contract is the starting gun. Bulk excavation is already under way, which means the civil and piling work is the live scope right now, and the structure, services and fit-out trades sit behind it in the queue. Until the contingency number is public, nobody outside the deal knows how much headroom is left if the ground, the steel or the labour market throws a curveball.
Frequently asked questions
What does Hobart’s Macquarie Point stadium now cost?
The core stadium build has risen to $1.23 billion. Once precinct works ($132 million) and project delivery costs ($183 million) are added, the total reaches $1.54 billion.
Why isn’t the contingency figure public?
The Tasmanian government and the Macquarie Point Development Corporation are keeping it confidential until the construction contract with BESIX Watpac is signed. Applying the same contingency rate as the previous budget would add roughly $215 million, for about $1.76 billion all up.
When will the construction contract be signed?
A contract with BESIX Watpac is due to be signed within weeks, with the new budget going to cabinet by 30 November.
Does the project still fit within the original $875 million state funding cap?
No. With $1.29 billion of the project cost now falling to Tasmanian taxpayers through capital and borrowings, the ABC reports the original $875 million cap has effectively been scrapped.
Sourced from ABC News. Original article.