Tasmania will build the Macquarie Point stadium in Hobart even if the Commonwealth, the AFL and Cricket Australia all knock back its request for more money, Treasurer Eric Abetz told a state parliamentary committee, with the government’s cost estimate now at $1.23 billion and a fixed-price construction contract scheduled to be signed on 18 December.

ABC News reported the committee hearing, which saw Mr Abetz and senior departmental staff front the public accounts committee. The stadium estimate has risen from $1.13 billion to $1.23 billion, with the Commonwealth tipping in $240 million towards the broader precinct and the AFL adding $15 million. Counting precinct and development costs, the total bill reaches $1.54 billion.

Asked by Labor’s Dean Winter whether the project would still go ahead if no extra money arrived from those parties, Mr Abetz answered: “That would be my expectation, yes.”

He would not say how much the state is prepared to spend in total. “We will indicate all of that once we know what the final price is,” he told the committee.

The $875 million cap that didn’t hold

Before last year’s final parliamentary vote on the stadium, Premier Jeremy Rockliff put a commitment in writing: the state’s contribution would be capped at $875 million. If the estimate rose, the government would either cut the stadium’s scope or go looking for money from the Commonwealth, the AFL or Cricket Australia.

That cap is now gone. Mr Abetz pointed to the “unforeseen” Iran war as the reason, and conceded the commitment would not be met.

“Are we able to abide by that commitment? At this stage, it doesn’t look as though we can,” he said.

That written promise was the price of independent MLC Bec Thomas’s support for the project. Speaking to ABC Radio Hobart, she said she stood by the deal anyway.

“It is clear that the cap of $875 million that I secured in order to support the stadium has influenced the behaviour of the Macquarie Point Development Corporation,” Ms Thomas said.

“Without having that cap in place, we wouldn’t probably be having these conversations.”

She added: “Ultimately, it’s the government who is accountable for whether or not it sticks to its promises, isn’t it?”

A construction worker in hi-vis reviewing drawings on a site table
Under a fixed-price head contract, escalation risk gets priced in, then negotiated down the chain into trade packages. Illustration: Blue Collar News

Macquarie Point Development Corporation, which is publicly owned, found $100 million of savings during the design stage. The government has since written to the Commonwealth, the AFL, Cricket Australia and Cricket Tasmania asking for more, but did not tell the committee whether anyone had written back.

”Higher margins” in the tenders, and what fixed price means down the chain

The clearest explanation of why the number moved came from Department of Premier and Cabinet secretary Kathrine Morgan-Wicks, who chairs the stadium oversight committee.

“As market uncertainty has increased, impacted by the Iran war, tenderers are seeking greater protection against future cost escalation and project risk than was anticipated in earlier estimates,” she told parliament.

“This has resulted in higher margins being included in tender submissions than had been assumed during previous planning phases.”

That is the part worth reading twice if you run a subcontracting business. The committee confirmed the head contract will be fixed price rather than cost-plus. Under a lump sum deal, the builder, in this case BESIX Watpac, which won the tender, wears the gap between the price it signs and what materials and labour actually cost by the time the job finishes. Under cost-plus, the client wears it.

Builders don’t absorb that risk for free. They price it, which is exactly what Ms Morgan-Wicks described happening in the tender submissions. On a multi-year job, the same question works its way down into the trade packages: who carries escalation on steel, concrete, cabling and labour between signing and handover, and whether a subcontract carries a rise-and-fall mechanism or a flat rate. Anyone pricing a package on a build this size wants that answered before they sign, not after.

The contingency figure for the project hasn’t been set yet. The previous contingency sat at an additional 14 per cent.

Steel fixers tying reinforcement on a large concrete deck
Steel, concrete and labour are the line items most exposed to escalation on a multi-year build. Illustration: Blue Collar News

Who signs, and with whose money

Murchison independent MLC Ruth Forrest pressed the Treasurer on how the development corporation could sign anything without guaranteed funding, noting that its chair “indicated quite clearly he was unable to sign a contract without surety of the funding required, and obviously it’s come in above what was agreed”.

Mr Abetz said the answer was borrowings. “The board will need comfort, and that comfort will be provided through a facility from (public financing corporation) TasCORP.”

No maximum borrowing limit has been set.

Ms Morgan-Wicks also flagged overseas interest in buying a 49 per cent stake in the Hobart Hurricanes Big Bash League club as a possible route to outside investment in the stadium. “Meetings that we’ve had with parties that are associated with that sale … we will be continuing to work through that over the coming months,” she said.

What to watch before 18 December

Cabinet makes its final call on the contract in the week leading up to 18 December. Until then, three things are unresolved: the contingency, the borrowing ceiling, and whether any of the parties the government has written to come back with money.

For Tasmanian trades, a signed fixed-price head contract is the trigger that turns a political argument into a procurement schedule, because trade packages get let off the back of an executed contract, not a cabinet intention. If you want the detail of the testimony itself, the public accounts committee is where it sits on the record. The number to watch next is the contingency, because that figure is the government’s own estimate of how much more it expects this to cost.

Frequently asked questions

Will the Macquarie Point stadium go ahead if Tasmania doesn’t get extra funding?

Treasurer Eric Abetz told a parliamentary committee that proceeding without extra money from the Commonwealth, the AFL or Cricket Australia would be his “expectation”.

Why has the Macquarie Point stadium cost gone up?

The government’s estimate has risen from $1.13 billion to $1.23 billion. Department secretary Kathrine Morgan-Wicks said tenderers built higher margins into their bids because of market uncertainty linked to the Iran war.

What happened to the $875 million cost cap on the stadium?

Premier Jeremy Rockliff had promised in writing to cap the state’s contribution at $875 million. Abetz told the committee it no longer looks achievable.

When will the fixed-price construction contract be signed?

Cabinet is due to make its final call in the week leading up to 18 December, when a fixed-price head contract with builder BESIX Watpac is scheduled to be signed.


Sourced from ABC News. Original article.