Early construction has started on the $400 million Canterbury Hospital Redevelopment in Campsie, the largest upgrade to the facility in more than 26 years, with TCQ Construction appointed to deliver the first phase.

The early works focus on expanding the existing antenatal unit, converting 316 square metres of basement car park into new clinical space, including additional ultrasound and consultation rooms. That expanded unit is scheduled to open in 2027, according to Mirage News.

The $400 million total reflects the NSW Government’s commitment after the 2026-27 Budget added $50 million to the original $350 million to fast-track maternity and special care nursery services. Health Infrastructure NSW is delivering the project in partnership with Sydney Local Health District. Planning approval for the early works was granted in April 2026, following a public exhibition of an environmental factors review late last year.

NSW Health Minister Ryan Park said the government was making record investments to deliver new and upgraded hospital infrastructure for communities like Canterbury. Member for Canterbury Sophie Cotsis said the community had waited for the upgrade for decades and was delighted to see construction activity starting on site.

The early works are the lead-in to a much larger main works package. That broader redevelopment will deliver a new nine-storey building housing a new ICU, expanded emergency department, additional surgical theatres, and new inpatient units, plus a three-storey eastern expansion. The main works planning application was on public exhibition through to mid-July 2026, so a head contractor appointment and full mobilisation are still to come.

For tradies across Sydney, the pipeline runs well beyond the current phase. Structural, fit-out, mechanical, electrical, and hydraulic trades will all be needed once the main works package is awarded. Canterbury is one piece of sustained demand for trade labour across NSW into the late 2020s.

Frequently asked questions

What does the first phase of the Canterbury Hospital Redevelopment involve?

The first phase, being delivered by TCQ Construction, converts 316 square metres of basement car park into new clinical space for an expanded antenatal unit, including additional ultrasound and consultation rooms. It’s scheduled to open in 2027.

How much is the Canterbury Hospital Redevelopment worth?

The total NSW Government commitment is $400 million. That figure increased after the 2026-27 Budget added $50 million to the original $350 million to fast-track maternity and special care nursery services.

What will the main works deliver?

The broader redevelopment includes a new nine-storey building housing a new ICU, expanded emergency department, additional surgical theatres, new inpatient units, and a three-storey eastern expansion. A head contractor has not yet been appointed.