Queensland civil contractor BMD Constructions has been appointed to carry out early works on Brisbane Stadium at Victoria Park, the centrepiece venue for the 2032 Olympic and Paralympic Games. The Games Independent Infrastructure and Coordination Authority (GIICA) announced the contract on 21 July following a two-phase open market procurement process that drew 22 responses at prequalification stage.
Bulk earthworks, erosion and sediment controls, haul roads, stormwater drains, retaining walls, semi-permanent fencing and a logistics plaza are all in scope. Works start in August 2026 and are scheduled to wrap by mid-2027. Engineering consultancy GHD has been appointed as the design and technical advisory partner for the early works package, according to The Urban Developer.
Founded in Queensland in 1979 by Mick Power, BMD has grown into a $2 billion operation employing more than 2,300 people. BMD Group CEO Scott Power said the company understood the weight of the project. “As a Queensland-founded, family-owned business, BMD is proud to deliver the Brisbane Stadium early works,” he said. GIICA CEO Simon Crooks said he looks forward to “creating Queensland jobs and building an extraordinary legacy with the new Brisbane Stadium in Victoria Park.”
The contract also carries an Indigenous supply chain commitment. BMD has engaged Indigenous-owned Bajara Plant Hire as a long-term partner for the civil earthworks component, with trainee pathways for Indigenous workers in civil construction and plant operations embedded in the contract.
The early works sit inside a much larger pipeline. Brisbane Stadium carries an estimated construction cost of $3.785 billion on its own, within a $7.1 billion Games Venues Infrastructure Program jointly funded by the Queensland and Australian governments. The main stadium design-and-construct contract hasn’t been awarded yet: two consortiums, Built Australia/Sacyr and John Holland/BESIX Watpac, are still in the Early Contractor Involvement phase. Stadium architects Cox Architecture, Hassell and Azusa Sekkei are working alongside structural engineers Arup and Schlaich Bergermann Partner. The finished venue will seat 63,000 in legacy configuration, expanding to 70,000 for concerts, and will serve as home ground for the Brisbane Lions, Brisbane Heat and Queensland Bulls.
For Queensland tradies and civil crews, the timing is immediate. Earthmoving operators, concreters, drainage and fencing trades will be in demand at Victoria Park from next month. The main stadium contract, when it lands, will open another significant run of work across virtually every construction discipline.
Frequently asked questions
When do works start on Brisbane Stadium and what trades are needed?
Works start in August 2026 and are scheduled to finish by mid-2027. Earthmoving operators, concreters, drainage and fencing trades will be in demand at Victoria Park from the outset.
How much will Brisbane Stadium cost to build?
Brisbane Stadium carries an estimated construction cost of $3.785 billion. It sits within a broader $7.1 billion Games Venues Infrastructure Program jointly funded by the Queensland and Australian governments.
Has the main stadium contract been awarded yet?
No. Two consortiums, Built Australia/Sacyr and John Holland/BESIX Watpac, are still in the Early Contractor Involvement phase. The design-and-construct contract hasn’t been awarded.
Sourced from Sourceable, The Urban Developer, Trade Earthmovers, Business News Australia. Original article.